Glatt GPCG-15 Installation at Par Pharmaceutical Manufacturer in Chestnut Ridge, NY.
Managed a portion of the installation. Assisted the project manager and the riggers with proper placement of the fluid bed components. Directed the electricians on all wiring of field devices, instruments and motor controls. CNE handled all of the control wiring inside the control panel and to all the field devices (including all pneumatic connections).
Once the wiring was complete, CNE executed a complete start up of the system, and also completed the validation (document written by OEM).